GlossaryFloor Operations

    Dispatch List

    Definition

    A dispatch list is the ordered list of operations a specific work center, machine, or operator should run next, taken from the current production schedule. In manufacturing it answers the floor's most common question, "What do I run after this job?" A typical dispatch list shows the sequence, job number, operation, part, quantity, planned start, due date and status for each line. A useful dispatch list is current, feasible, and visible at the machine; a list printed at the start of the shift goes stale as soon as the floor changes.

    Example dispatch list

    Here is what a dispatch list for one shift can look like. The data below is a generic example, not from a real shop.

    Sample dispatch list (generic example data)
    Work centerSeqJobOperationPartQtyPlanned startDue dateStatus
    5-axis mill (WC-110)1J-1042Op 20: Finish millBRKT-00140Mon 6:00 AMWedRunning
    5-axis mill (WC-110)2J-1057Op 10: Rough millHSG-01412Mon 9:30 AMThuReady
    5-axis mill (WC-110)3J-1038Op 30: Drill and tapPLT-20325Mon 1:15 PMFriWaiting on material
    CNC lathe (WC-210)1J-1049Op 10: Turn ODSHFT-00760Mon 6:00 AMTueRunning
    CNC lathe (WC-210)2J-1061Op 10: Turn and boreBSHG-022100Mon 11:00 AMThuReady
    CNC lathe (WC-210)3J-1042Op 30: Turn bossBRKT-00140Mon 3:30 PMWedWaiting on prior op

    Each work center has its own list, sorted by sequence. The status column tells the operator what is running, what is ready to set up, and what is blocked. When the schedule changes, the sequence and planned start times change with it.

    Why it matters

    The dispatch list is where the schedule meets reality. If it is wrong, operators improvise; if it is right, the floor runs the planned sequence. Many shops still publish dispatch lists once per shift on paper, then watch operators drift from them as the day changes. A dispatch list that is republished with every recompute — on demand, on ERP event, or continuously where wired — is the single largest visible behavior change a scheduling engine produces.

    Common failure mode

    The dispatch list is printed at 6 a.m. By 9 a.m. a hot job has been inserted verbally, two operations have run long, and a machine is down. The printed list no longer matches the supervisor's instructions. Operators run by gut for the rest of the shift, and the system reports on-plan execution.

    How Skody handles it

    Skody generates the dispatch list for each work center live from the finite-capacity schedule, so it always matches the current plan rather than a morning printout. When a machine goes down, Skody recalculates the schedule (runtime depends on data volume, constraint complexity and deployment), moving affected work to qualified alternate machines where available or to the next feasible slot. The updated dispatch list shows the new sequence and machine assignments. When a hot job lands, Skody inserts it and re-sequences the work behind it. The schedule also recalculates on demand, when the ERP changes, or continuously where the floor is connected.

    Related in Skody: Scheduler · Finite-capacity scheduling · Machine shop scheduling software · Production dashboards

    Questions

    A dispatch list is the ordered list of jobs and operations a work center, machine, or operator should run next. It comes from the production schedule and usually shows the sequence, job, operation, part, quantity, planned start, due date and status.

    A schedule sets the timing and sequence of every operation across all resources. A dispatch list is one work center's slice of that schedule: the next jobs to run there, in order. If the schedule changes and the dispatch list doesn't, operators end up running yesterday's plan.

    At minimum: the work center, the sequence, the job and operation, the part and quantity, the planned start, and the due date. Useful additions are status (running, ready, waiting on material or a prior operation) and setup notes, so the operator can prepare tools and fixtures for the next job.

    Whenever a floor event changes the best sequence: a machine going down, a job running long, material arriving late, or a hot order. When a machine goes down, Skody recalculates the schedule (runtime depends on data volume, constraint complexity and deployment), moving affected work to qualified alternate machines where available or to the next feasible slot. The updated dispatch list shows the new sequence and machine assignments.

    See dispatch list in your shop

    Run the Production Clarity diagnostic and see which scheduling constraints are costing you OTD today.

    Take the Diagnostic