Definition
A dispatch list is the ordered list of operations a specific work center, machine, or operator should run next, taken from the current production schedule. In manufacturing it answers the floor's most common question, "What do I run after this job?" A typical dispatch list shows the sequence, job number, operation, part, quantity, planned start, due date and status for each line. A useful dispatch list is current, feasible, and visible at the machine; a list printed at the start of the shift goes stale as soon as the floor changes.
Example dispatch list
Here is what a dispatch list for one shift can look like. The data below is a generic example, not from a real shop.
| Work center | Seq | Job | Operation | Part | Qty | Planned start | Due date | Status |
|---|---|---|---|---|---|---|---|---|
| 5-axis mill (WC-110) | 1 | J-1042 | Op 20: Finish mill | BRKT-001 | 40 | Mon 6:00 AM | Wed | Running |
| 5-axis mill (WC-110) | 2 | J-1057 | Op 10: Rough mill | HSG-014 | 12 | Mon 9:30 AM | Thu | Ready |
| 5-axis mill (WC-110) | 3 | J-1038 | Op 30: Drill and tap | PLT-203 | 25 | Mon 1:15 PM | Fri | Waiting on material |
| CNC lathe (WC-210) | 1 | J-1049 | Op 10: Turn OD | SHFT-007 | 60 | Mon 6:00 AM | Tue | Running |
| CNC lathe (WC-210) | 2 | J-1061 | Op 10: Turn and bore | BSHG-022 | 100 | Mon 11:00 AM | Thu | Ready |
| CNC lathe (WC-210) | 3 | J-1042 | Op 30: Turn boss | BRKT-001 | 40 | Mon 3:30 PM | Wed | Waiting on prior op |
Each work center has its own list, sorted by sequence. The status column tells the operator what is running, what is ready to set up, and what is blocked. When the schedule changes, the sequence and planned start times change with it.
Why it matters
The dispatch list is where the schedule meets reality. If it is wrong, operators improvise; if it is right, the floor runs the planned sequence. Many shops still publish dispatch lists once per shift on paper, then watch operators drift from them as the day changes. A dispatch list that is republished with every recompute — on demand, on ERP event, or continuously where wired — is the single largest visible behavior change a scheduling engine produces.
Common failure mode
The dispatch list is printed at 6 a.m. By 9 a.m. a hot job has been inserted verbally, two operations have run long, and a machine is down. The printed list no longer matches the supervisor's instructions. Operators run by gut for the rest of the shift, and the system reports on-plan execution.
How Skody handles it
Skody generates the dispatch list for each work center live from the finite-capacity schedule, so it always matches the current plan rather than a morning printout. When a machine goes down, Skody recalculates the schedule (runtime depends on data volume, constraint complexity and deployment), moving affected work to qualified alternate machines where available or to the next feasible slot. The updated dispatch list shows the new sequence and machine assignments. When a hot job lands, Skody inserts it and re-sequences the work behind it. The schedule also recalculates on demand, when the ERP changes, or continuously where the floor is connected.
Related in Skody: Scheduler · Finite-capacity scheduling · Machine shop scheduling software · Production dashboards
Related terms
Questions
See dispatch list in your shop
Run the Production Clarity diagnostic and see which scheduling constraints are costing you OTD today.
Take the Diagnostic